You need to overclock: 13 Biomass Burner at 250%, 1 Biomass Burner at 200%.

You need to underclock: 1 Biomass Burner at 23.333%.

Fuel input
Build Cost

You need to overclock: 6 Coal Generator at 250%.

You need to underclock: 1 Coal Generator at 49.333%.

Fuel input
Supplemental Load
Build Cost

You need to overclock: 3 Fuel Generator at 250%.

You need to underclock: 1 Fuel Generator at 24.667%.

Fuel input
Build Cost

You need to underclock: 1 Nuclear Power Plant at 46.48%.

Fuel input
Supplemental Load